Upson Hall Renovation

in this section


Frequently Asked Questions

Submit a Question or Concern

This issue is authored by the Cornell University Infrastructure, Properties, and Planning Construction Management Team.

Project Status

The second phase of the Upson Hall renovation project is well underway and we are pleased to inform you we are getting closer to seeing a complete, functional building. The construction team continues to work diligently to complete the remainder of the project while addressing items still outstanding.

Some of the major improvements since our last update include the rework of the entire vestibule area close to the Duffield Atrium and the installation of new fire-rated storefronts doors. In addition to providing more access to the building via the freight and passenger elevators, we are happy to confirm that the open stair at the northeast (Stair B) will open to provide access to Floors 3, 4 and 5.

Regarding construction, general activities and impacts projected for the next several weeks include:

1.    Interior framing and installation of drywall for new spaces.

2.    Installation of major building utility infrastructure on all floors.

3.   Completion of window surrounds on the exterior.

4.    Installation of the vapor barrier and terracotta clips is underway.

5.   Ongoing completion of mechanical piping installation.


REMINDER - Pike's regular work hours are 5 a.m. to 3:30 p.m.  They will try to restrict the "most disruptive" noise to the hours of 5 a.m. to 8 a.m., but that is subjective.  There will be construction noise at any/all times during their working hours.  

The contractor's more detailed schedule for the next two weeks is as follows.

 BASEMENT 

1.     Demolition of exterior wall is now complete and underground piping has been installed.

2.     Windows have been installed.

3.     Testing of plumbing continues in preparation for new sprinklers.

4.     Mechanical piping is now installed.

 

FIRST FLOOR

1.     Demolition is complete and some openings are covered by temporary protection.

2.     Layout of the floor area is complete and interior framing is ongoing

3.     MEP rough-in continues in preparation for duct work on the ceiling deck.

 

SECOND FLOOR

1.     Interior framing is complete and dry wall is being installed.

2.     MEP rough-in of duct work is underway starting with the duct risers that bring air to the entire floor.

3.     Framing for custom ceilings is ongoing.

4.     Taping and finishing of drywall.


EXTERIOR

1.     Installation of the terracotta system is ongoing.

2.     Exterior waterproofing and drainage is nearing completion.

3.     Window surround on bump-outs are being installed.


New Egress Plan/First Floor Emergency Exits 

After the move, the path in and out of the building will change. Below is an egress plan to guide you through the building.

Download PDF of Egress Plan

 

  What to do:

If you experience issues that need attention, please submit a ticket using the Facilities Ticket button on the left (or the usual ticket system). Tickets submitted this way are reported via text message and email alert to several facilities staff.

You can also contact the CoE/CIS Facilities office at 255-5668. Thank you for your patience and cooperation. 

We hope that ultimately being in your new space will make this stressful time period worth it.

www.engineering.cornell.edu/about/

We will have the archive of all updates located here:       June 19, 2015

July 2, 2015

July 17, 2015

July 31, 2015

August 14, 2015

September 18, 2015

October 2, 2015

October 16, 2015

November 2, 2015

December 4, 2015

January 29, 2016

March 11, 2016

April 20, 2016

July 22, 2016

December 12, 2016

February 3, 2017